Planning FAQs - When does my permit expire, and can I extend it?

Answer

A Planning Permit will expire when a development, a use or subdivision approved by that Planning Permit is not carried out within the specified timeframes.

These timeframes are usually set out in a condition of the permit. The timeframes specify dates for commencing and completing the requirements of the permit.

A request can be made to Council to extend these timeframes:

  • Before the permit expires, or
  • Within 6 months after the permit expires, or
  • Within 12 months after the permit expires, if the development lawfully commenced before the expiry date and you wish to extend the time to complete the development. Evidence to show works have commenced may be requested by the Council Officer assessing the application.

Contact Council for further information on what is required for an extension.